Plan Material Requirements

Material Requirements finds shortages across your planned work and turns them into documents. It is a lightweight (MRP-lite) alternative to a full MRP system, netted by week.

Run a check​

  1. Go to Manufacturing Planning → Material Requirements → New Run. Running or firming needs the Create Work Orders permission.
  2. Choose a horizon with From and To dates.
  3. Leave Include Inventory demand forecast on for planned demand. If Demand and Replenishment Pro or Enterprise Supply Chain Optimization is licensed and a saved BOM explosion exists in the horizon, planned demand uses it. Otherwise the run uses your sales and usage history. The run does not rebuild the Supply Chain forecast.
  4. Firm demand is the exploded quantity of Planned and Released work orders (dated by planned start). When Create work orders from sales orders is on, it also includes uncovered quantity on confirmed or partially fulfilled sales orders. Stocked finished goods are not exploded into components.
  5. The run nets demand against on-hand stock, open purchase orders, issued materials and forecast. The details page shows Firm and Planned columns and a weekly grid.

Raise documents​

  • Raise Work Order creates a draft work order for finished or semi-finished items with an Active BOM.
  • Raise PR creates a purchase requisition for raw materials.
  • Raise Transfer creates a draft stock transfer where another warehouse can cover the shortage.
  • Firm on a week cell firms that week.

A second click returns the same document rather than creating a duplicate.

For purchase lines the run also shows Order by under the needed-by date: the needed-by date minus the preferred supplier's lead time, in red when it is today or past. The suggested quantity is raised to the supplier's minimum order and pack size, and Raise PR names the supplier.

To have requisitions raised for you, turn on Raise requisitions after the weekly MRP run in the Manufacturing settings. After the Monday run, every purchase line due to be ordered within 7 days gets a draft requisition.

Review the run​

Use Mark Reviewed and Mark Actioned to advance the status. Firming marks the run Actioned.

:::info A run is a snapshot, not a live plan Past runs stay listed but do not recalculate. Re-run whenever work orders, sales orders, forecast or stock change. An overloaded workstation (over 100 percent) shows a capacity warning on the run and on work order save, without blocking either. :::

Next step​