Skip to main content

Running a Work Order from Start to Finish

A work order is the shop-floor job: what to make, how many, and which recipe (BOM) to use. This article is the short version; Create and run a work order has every status and rule.

The lifecycle​

Draft → Released → In Progress → Completed → Closed

1. Create the work order​

  1. Go to Manufacturing Planning → Work Orders → Create.
  2. Select the finished item, an Active BOM, the quantity and target dates.
  3. Save. The order is a Draft and loads its components from the BOM.

2. Release it​

Click Release. This checks that the BOM has lines and unlocks material issuing.

3. Issue materials​

From the work order's Details, click Issue materials for a pre-filled material issue. Posting it reduces raw stock at the source warehouse.

4. Record production​

Use Report production to log good, rejected, rework and scrap quantities. Completing the entry increases finished goods stock.

:::tip Prefer fast, real-time capture? The Shop Floor Terminal lets operators tap Good, Reject, Rework and Scrap from any browser and rolls everything into one production entry when the session completes. :::

5. Complete and close​

Click Complete work order once output is done, then Close order to finalize. Closing is final.

If something goes wrong​

  • Pause: use Put On Hold, then Resume.
  • Cancel: needs a reason, returns issued materials to stock and reverses their journals. It is not possible once production entries are completed.